Hurd St. Courthouse Demolition Approved for 6-story housing Development

The District Courthouse, which has been vacant since 2020, will be demolished in the summer of 2027. (Courtesy Melanie Gilbert for Inside Lowell)

by Melanie Gilbert

LOWELL – The city’s three land-use boards approved the demolition of and the variances and rebuilding site plans for the former District Courthouse on Hurd Street in the city’s historic downtown area.

The unanimous votes took place with the Historic Board on Oct. 19, the Zoning Board on Oct. 26 and the Planning Board on Nov. 2, The votes move the housing development closer to reality on a parcel that has been vacant since 2020.

“This is about as good of an application as I’ve ever seen submitted,” Plannng Board Vice Chair Gerard Frechette said during the November public hearing. “I love the look of the building. It has a traditional look, but yet you’re incorporating some modern looks as well.”

New England Heritage Properties Inc., was the developer chosen for the site through the city’s 2025 request for proposal process to bring a mixed-use residential development into the historic neighborhood.

Development of the former state-owned parcel also meets the goals in the city’s Lowell Forward Master Plan.

Rendering of the six-story, mixed-use building of approximately 205 market-rate rental units at 41 Hurd St. in Lowell’s historic downtown district. (Courtesy New England Heritage Properties Inc.)

Heriatge Properties plans to build a six-story, mixed-use building of approximately 205 market-rate rental units at 41 Hurd St., at the intersections of Hurd, Goerge and William Streets.

“It’s a mix of studios, one-bedroom, and two-bedroom units,” President Jeff Bush told the Planning Board. “We have two commercial spaces of around 6,000 square feet of proposed commercial use.”

Heritage Properties is a development and property management company that was founded in Lowell by Bush’s grandfather and a partner in 1978. The company was last before the board in 2024 for a project on Middlesex Street known as The Emery, which opened this fall. Heritage Properties also redeveloped a housing project on Lawrence Street called Waterhead Mill in 2019.

The $76-million Hurd Street investment consists of approximately 57,000 square feet of land on which the U-shaped building will sit.

Area neighbors to the site include UTEC, which helps young people overcome the challenges of poverty, gang involvement and unemployment. The former UMass Inn and Conference Center sits below grade off Warren Street. The nine-story building is currently vacant, but the UMass Building Authority, an independent state body that owns the ICC, meets Wednesday to determine its fate.

The city favors housing development on that site that also has a large surface parking lot.

About two blocks away is Central Plaza, a shopping mall featuring a range of retail stores.

And diagonal to the site is the city-owned Lower Locks Garage, an almost 1,000-space facility that Bush said would augment the project’s 36 off-street parking spaces – a 15-space surface lot and a 21-space first-floor covered parking.

“We’ve requested, and we’ll negotiate with the city for 300 of those [Lower Locks] spaces to be reserved for tenant use so that there’s always capacity for this project on a long-term basis,” Bush said.

The building will be amenity rich with a community room, theater room, fitness center, a courtyard and a bike room. Bush said the commercial spaces had not been “programmed yet,” but he anticipated “some kind of food and beverage location, whether it be a cafe, a restaurant, a quick serve, and some type of studio fitness – think soul cycle, yoga studio, barre class.”

The apartment building would be pet-friendly and include a dog run for supervised pet activity.

Approval from the Historic Board Oct. 19, required elements of the old courthouse to be incorporated into the future building.

The design team said a working historic wall clock was found in the main courtroom that could be showcased in the building someplace, as well as the medallion on the exterior wall over the Hurd Street entrance.

“We thought that was would make a good exterior garden piece with maybe a plaque to emphasize the importance, the historic features of it, and the reason it was there to begin with,” Aubrey Bennett, with Market Square Architects, said at the October Historic Board meeting.

Bush told the Planning Board that asbestos abatement would take place before the demolition next summer.

Once the site was cleared, Bush said he expected construction to take two to three years and a year to lease up.

“So, if all goes well in July of 2029, we’d be welcoming our first residents,” he said.